Projects where North Mechanichal Innovation AS have participated:
DIHC
- Drillco Inline Heave Compensator for Drillco AS
In January 2009, NMI has taken over the completion of the DIHC for Drillco AS. The project had stalled and Drillco needed the DIHC ready for operation by 1st of April 2009.
Read more...
Salvage
tooling pack for Neptun Subsea AS
In August 2008 the NMI AS got contract to supply tooling pack which is suitable for marine-salvage Neptun Subsea AS.
Read more...
Seaflex mount bracket for Seaflex AS
Current Sensor Deployment System for Oceanor AS
IP66 Pantilt FUGRO - Development / design
Eex d Pantilt GASOPTICS Development / design
SS IP66 Camera OCEANOR Development / design
IMCT - Internal Multistring Cutting Tool for NORSE CUTTING AND ABANDONMENT AS Development / design
Eex d Pantilt OCEANOR Development / design
Coiltubing units HITEC as – building / commissioning
Magnum umbilical winches OCEANEERING
Wastewaterunits CETCO
Combo- winch KOS
Umbilical winch HITEC AS
ROV-garage Mounting for West Navion
SSTV-winch West
Navion
Wireline-winches
SMEDVIG
Conductor
jacking system NORSE Cutting &
Abandonment AS
Umbilical winch ROVCO AS
The Motor
for umbilical winch ROVCO AS
Modification of personal winch BRAGE
Cutting Equipment KURSK
Development, design
and production of Ex camera station, Fugro OCEANOR
Design and production of Ex coax-connector, Technor ASA
Development, design and production of inklinometer bracket for mounting on drilling-riser ,
SeaFlex AS
Development, design and production of the smear-machine, Gilde Vest
ROV-Winch
OCEANEERING
Developed
and produced management for the winding device so that it can handle
all dimensions of the control cable for ROV. You can also use a
joystick to override the winding machine and when you are finished the
automatic system remembers the new position of the winding machine and
stays there. The control is fully hydraulic and therefore it can be
used in EX areas.
Flange Cleaning
Gear
This is a unit that operates in depth of up to 450 meters in connection with the remote-controlled mini-submarine (ROV).
Powder transport
NORZINK
Cutting equipment for linear-cutting, ”KURSK”
Mission Monday, 9th of
November,
Year 2000, 10am.
To develop a device that keeps the water- "cutter" equipment for the
linear- motion up to 2500mm and that the divers can operate easily.
To deliver the equipment within the deadline which was Friday, 13th of November, 4pm.
The equipment was delivered in time.
An equipment for the hole- cutting, ”KURSK”
Mission Monday, 9th of November,
Year 2000, 10am.
To develop a device that keeps the
water- "cutter" for the circle-motion at 50-200mm and that divers can operate easily.
To deliver the equipment within the deadline which was Friday, 13th of November, 4pm.
The equipment was delivered in time.
|